Year: 2025
Ariel Footage
Week 46
One Step Forwards, One Back…
Issues Identified…
The site meeting this week revealed a number of defects in the construction phase, some minor but unfortunately some major. However, thankfully they were all spotted in good time and are relatively easy to remedy. The most critical structural issue was the installation of the steel posts, that support the…
Week 43
First Floor Slab Poured
First floor slab signed off
First floor slab
Ground floor slab poured
Construction has reached a key milestone with the ground floor concrete slab now poured, providing a solid foundation for the structure above. Installation of structural posts has already commenced, beginning to shape the building’s framework and support future levels. At the same time, waterproofing is being applied to the basement…
Ariel Footage
Week 46
One Step Forwards, One Back…
Issues Identified…
The site meeting this week revealed a number of defects in the construction phase, some minor but unfortunately some major. However, thankfully they were all spotted in good time and are relatively easy to remedy. The most critical structural issue was the installation of the steel posts, that support the…
Week 43
First Floor Slab Poured
First floor slab signed off
First floor slab
Ground floor slab poured
Construction has reached a key milestone with the ground floor concrete slab now poured, providing a solid foundation for the structure above. Installation of structural posts has already commenced, beginning to shape the building’s framework and support future levels. At the same time, waterproofing is being applied to the basement…