Month: January 2025
Rain Stops Play…
Week 12
Good progress of earthworks which is now around half way to the basement slab level. A temporary brace is installed between the rear and east pile walls, during construction. The project manager, architect and developer have been discussing the possibility of installing gabion walls, instead of concrete rendered walls, which…
Week 11
Rain Stops Play…
Week 12
Good progress of earthworks which is now around half way to the basement slab level. A temporary brace is installed between the rear and east pile walls, during construction. The project manager, architect and developer have been discussing the possibility of installing gabion walls, instead of concrete rendered walls, which…


