Great to come and see the site in person, especially when you consider the last visit was before the basement foundations had even been created. Whilst the photos give a really good idea of progress and scale, nothing replaces seeing the progress in real life. Talking of life, if you…
An unexpected update today from the project manager, who has been on site to inspect the roof, before concrete is poured tomorrow. This will mark a major milestone in the build, with the core structure now complete activity will move onto blockwork and waterproofing.
An ad-hoc site visit by the project manager today, as the normal Monday site meeting between all parties fell on a public holiday. Great to see the master suite slab has been poured and the roof posts have already been cast. Progress has also been made on some other elements…