First floor slab

As is customary, August saw the a number of people, including our project manager, taking a couple of weeks off – so this update covers three weeks of progress. All of the pillars on the ground floor slab have been finished and the supporting formwork installed for the 1st floor…

Continue reading

Ground floor slab poured

Construction has reached a key milestone with the ground floor concrete slab now poured, providing a solid foundation for the structure above. Installation of structural posts has already commenced, beginning to shape the building’s framework and support future levels. At the same time, waterproofing is being applied to the basement…

Continue reading

Week 37

Work has stalled slightly on the ground floor slab, with only work on the rear half, as a number of the posts at the front of the basement were demolished due to defects. The formwork has just started to be installed in the front section, where the outdoor kitchen will…

Continue reading