Week 30

The basement slab steelwork is now complete, with the following photos showing the overall basement, plus the swimming pool that will jut outwards from the villa with views towards Gibraltar. A photo the following day shows the completed concreting of the basement floor slab. Work now stars on the basement…

Continue reading

Week 28

The blinding layer of concrete has been poured and reinforced steel starting to be placed for the basement slab. You can really start to get the sense of scale now this has been marked out.

Continue reading

Week 24

The ecological walls have been finished and the excavations are also now complete. This clearly shows what the final garden levels will look like in the future. Not long now until the work on the basement slab commences and all the earthworks complete.

Continue reading

Week 23

This week the crane base has been installed in the pit. The base will be concreted in place, acting as the counterbalance, with the tower attached to the posts. The base will remain in place and buried, once the crane has been removed at the end of the build. More…

Continue reading