Some more great progress over the last week, with the steel reinforcing installed in the master suite slab. This is now ready for concreting later on this week, which will take a few truck loads, as it is 450mm deep.
After this it is only the roof to go before the main structural work is completed.
You can also see the concrete perimeter retaining wall being formed (bottom right photo), which will then be faced with gabion stone work to match the rest of the perimeter walls. Also started this week is the formwork being installed for the west side set of stairs to take you from the ground floor terrace to the basement garden.