Rain Stops Play…

More earthworks this week, but it is all a little slow with significant number of storms in the Malaga area (albeit you wouldn’t be able to tell from these photos!). It has made getting up and down the bare earth path impossible for heavy machinery.

Continue reading

Week 12

Good progress of earthworks which is now around half way to the basement slab level. A temporary brace is installed between the rear and east pile walls, during construction. The project manager, architect and developer have been discussing the possibility of installing gabion walls, instead of concrete rendered walls, which…

Continue reading

Week 11

Following a shutdown over the Christmas holiday, the concrete tie beam has been completed at the mid point of the rear wall and also the capping beam on the east pile wall. Concreting has also been done on the higher of the two west wall capping beams and the excavation…

Continue reading